Construction Update

Construction at Oakridge Park continues to progress well. The Phase 1 North West parkade is complete and we have now reached grade on the foundation of the Community Centre and Buildings 1 and 2. The main raft foundation of Oakridge x Castiglia was poured at the end of June and Oakridge x Lissoni will be poured mid-month. Work has now commenced on the parkade slabs of the two buildings.

The Phase 1 South parkade is on schedule with the raft foundations for both Oakridge x Westbank and Oakridge x Clemande now complete. The majority of the first level of the parkade is complete and the second level is being formed. Demolition work on the mid-section of the mall is well underway and the North East Office building is currently being prepared for demolition.

Watch our progress video to see the latest evolution of the site.

Left Menu Icon